The text

At the conclusion of the inquiry, the judge shall make his report and order which shall state his finding and direct the payment into a bank, to be specified by him, of the amounts, if any, so found to be due, and the costs, within ten days thereafter, and in default of such payment, that the logs, timber or lumber, shall be sold by the sheriff for the satisfaction of the amount found due to the several parties upon the inquiry.