Pipeline Act, 2005, c. P-8.5
Section 29
Ground disturbance over or near pipeline
Cite as Pipeline Act, 2005, c. P-8.5, s. 29 · current to June 6, 2025 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Any person proposing to undertake or undertaking a ground disturbance shall, before commencing any work, operation or activity,
(a) take all precautions reasonably necessary
(i) to ascertain whether a pipeline exists within
(A) the area in which the person proposes to undertake or undertakes the ground disturbance, and
(B) the distance, prescribed in the regulations, from the area referred to in clause (A), and
(ii) to determine which permittee or licensee owns or operates any pipeline in existence within the area or distance referred to in subparagraph (a)(i), and
(b) notify the permittee or licensee of the nature of the proposed ground disturbance and the proposed schedule for undertaking it.
(2) When requested by a person proposing to undertake a ground disturbance, a permittee or licensee shall provide that person with any information about a pipeline in existence within the area or distance referred to in subparagraph (1)(a)(i) that is contained in its records and that is required by the person in order to comply with subsection (1) and the regulations.
(3) A permittee or licensee that may be or is affected by a ground disturbance shall provide the person proposing to undertake the ground disturbance with any assistance that the person may reasonably require to enable that person to comply with this Act and the regulations.
(4) Where contact is made with a pipeline during any ground disturbance, resulting in a puncture of or crack in the pipeline, or in a scratch, gouge, flattening or dent on the surface of the pipeline, or in damage to its protective coating, the person who is carrying out the ground disturbance shall stop the activity and shall immediately advise the permittee or licensee of the location where the contact occurred and the kind of damage that resulted from the contact.
(5) Where a ground disturbance has been stopped under subsection (4), no person shall recommence it without the approval of the permittee or licensee or, if approval cannot be reasonably obtained from the permittee or licensee, without the approval of the Board.
(6) When damage to a pipeline occurs as a result of a contact described in subsection (4), the Board may require the submission of reports in writing from such persons as it may specify, and those persons shall submit the reports required by the Board.