Pipeline Act, 2005, c. P-8.5
Section 24
Change to existing pipeline
Cite as Pipeline Act, 2005, c. P-8.5, s. 24 · current to June 6, 2025 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Where a licensee wishes to extend, relocate, divert or otherwise change an existing pipeline, it shall submit an application for a permit to the Board.
(2) An application under subsection (1) shall be made and dealt with by a procedure to be determined by the Board.
(3) Subsection (1) does not apply to
(a) repairs or maintenance made in the ordinary course of operation,
(b) minor improvements to an existing installation, or
(c) changes made in an emergency.
(4) Where changes are made to a pipeline in an emergency, a licensee shall immediately forward particulars of the changes to the Board.