Limitation of Actions Act, c. L-8.5

Section 22

Delay caused by defendant

Cite as Limitation of Actions Act, c. L-8.5, s. 22 · current to June 12, 2026 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

If the relevant limitation period established by this Act has expired, but the actions taken or assurances given by the defendant or the defendant’s agent in relation to the resolution of the claim before the expiry of the limitation period caused the claimant to reasonably believe that the claim would be resolved by agreement and therefore to delay bringing the claim, the claimant may bring the claim within 6 months after the day on which the claimant first knows or ought reasonably to know that the belief was unfounded.
Read the Limitation of Actions Act on the Province's website ↗