Highway Act, c. H-5

Section 63

Penalty clauses in contracts of Minister

Cite as Highway Act, c. H-5, s. 63 · current to June 12, 2026 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) A contract to which the Minister is a party, for the construction or maintenance of a highway that specifies a date by which or a time within which any work shall be done or material shall be supplied may also provide for a penalty for failure to complete the work or supply the material by that date or within that time. (2) The penalty referred to in subsection (1) shall be (a) the actual loss or damages suffered by the Crown because of the failure, or (b) a stipulated sum for each day that the work is unfinished or the material not supplied in full after the date or time agreed upon, regardless of actual loss or damages; or both (a) and (b). (3) Where a contract for the construction or maintenance of a highway provides for a penalty as mentioned in this section, the amount of the penalty may, to the extent thereof, be withheld from any money payable by the Crown under the contract.
Read the Highway Act on the Province's website ↗