General, N.B. Reg. 91-191
Section 180
Underground utility lines or piping and utility poles
Cite as General, N.B. Reg. 91-191, s. 180 · current to June 30, 2026 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Before beginning an excavation or trench, an employer shall ensure that the location of any underground utility line or piping is determined.
(2) Where employees are working within 600 mm of underground utility line or piping, an employer shall ensure that
(a) the authority operating the utility line or piping has been notified of the operation,
(b) the utility line has been de-energized, and
(c) an adequate operating procedure is used by the employees.
(3) An employer shall ensure that utility poles, posts and similar structures are supported or removed if they are within 3 m of an excavation or trench that is more than 1.2 m deep.
Read the General on the Province's website ↗
Made under Occupational Health and Safety Act, c. O-0.2.