Water Well, N.B. Reg. 90-79

Section 19

Cite as Water Well, N.B. Reg. 90-79, s. 19 · current to June 13, 2012 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) From the top of a dug well to a distance at least two metres below the immediate land surface, the annular space between the casing or rocked-up portion of the well and the surrounding side walls of the excavation shall be filled with clean washed gravel, sand, crushed rock or small boulders. (2) Any portion of the annular space between the casing or rocked-up portion of a dug well and the surrounding side walls of the excavation not filled with the materials referred to in subsection (1) shall be filled with cement grout, concrete, bentonite or equivalent commercial slurry, clay slurry or puddled clay to prevent surface waters from getting into the well.
Read the Water Well on the Province's website ↗

Made under Clean Water Act, c. C-6.1.