General, N.B. Reg. 86-98
Section 29
Feasibility study report
Cite as General, N.B. Reg. 86-98, s. 29 · current to March 30, 2026 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) A feasibility study report required under subparagraph 68(1)(c)(i) of the Act shall contain the following:
(a) a list of the names and mailing addresses of the lessee, its agents and the mine manager;
(b) a summary of the study including an assessment of the feasibility of production;
(c) a description of the geographic setting of the lease area including a map at a scale of 1:50,000 showing the boundaries of the lease area in relation to topographic features;
(d) a detailed description of the geological setting and minerology of the deposit to be mined;
(e) a list of the minerals or products to be mined or produced;
(f) a list of ore types and reserves thought to exist in the deposit to be mined, classified as proven, probable or possible;
(g) an up-to-date summary of annual exploration and development expenses;
(h) a summary of drilling and underground development and exploration work performed with results and assays;
(i) a summary of surface work performed with results and assays;
(j) a description of bulk sampling performed with assays and comparisons of assays;
(k) a description of pilot plant and metallurgical tests performed with results;
(l) a summary of marketing studies performed;
(m) the rationale for adopting a particular mining technique;
(n) a detailed description of the proposed mining plan including mining methods, rate or production, grades, recoveries, efficiencies and mining costs;
(o) a description of the proposed infrastructure;
(p) a list of required equipment;
(q) a description of the proposed processing methods and costs, including metallurgical flow sheets and recoveries;
(r) an assessment of the feasibility of processing the ore to the prime metal or finished product stage within the Province;
(s) an assessment of land requirements;
(t) an assessment of transportation requirements, including required access roads or rights of way;
(u) an assessment of power requirements and availability;
(v) a description of the proposed townsite, including housing, where applicable;
(w) an assessment of the potential social and economic impact of the project including the type and amount of labour required during construction and operation, wages and salaries to be paid, goods and services to be provided to the mine site and townsite, where applicable, including schools and hospitals, and the development of secondary industries;
(x) a forecast of sales revenue;
(y) estimates of capital and of annual operating costs;
(z) an evaluation of the project’s potential to generate sufficient cash flow to meet its operating costs, tax payments and debt servicing obligations;
(aa) scheduling;
(bb) under separate cover, a program for protection, reclamation and rehabilitation of the environment in accordance with section 30; and
(cc) such other information as may be relevant to the feasibility of the project or as may be required by the Minister.
(2) Where applicable, the data required in subsection (1) shall be shown on maps, sections or both.
(3) A feasibility study report shall be submitted in duplicate and shall comply with the requirements of paragraphs 17(1)(a), (b), (c) and (d) and subsection 20(1).
Read the General on the Province's website ↗
Made under Mining Act, c. M-14.1.