General, N.B. Reg. 86-98
Section 25
Plans and sections to be kept
Cite as General, N.B. Reg. 86-98, s. 25 · current to March 30, 2026 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
An owner shall cause the following plans to be kept and updated every three months on a scale acceptable to the Minister:
(a) a surface plan showing the boundaries of the property, the surface extent of the deposit being mined, all lakes, streams, roads, railways, electric power transmission lines, main pipelines, buildings, shaft openings, adits, dumps, tailings disposal sites, slag piles and open surface workings including pits, quarries and strip mines;
(b) underground plans of each level showing all underground workings, including shafts, drifts, crosscuts, raises, declines, inclines and diamond drill holes, and depicting each level in a separate illustration;
(c) vertical sections showing all shafts, drifts, raises, stopes and other workings in relation to the surface and to the top of the bedrock; and
(d) geological plans that are acceptable to the Minister and are conformable with the plans required in paragraphs (b) and (c).
Read the General on the Province's website ↗
Made under Mining Act, c. M-14.1.