(1) The owner of a boiler that is not to be included in determining the total therm-hour rating of a heating plant or power plant shall have the boiler disconnected and notify the Chief Inspector that the boiler is to be isolated.
(2) Every boiler that is not included in determining the total therm-hour rating of the heating plant or power plant shall be isolated by a boiler inspector by sealing the boiler in such a manner that it is incapable of being used without removal of the seal.
(3) No person shall remove a seal that has been affixed to a boiler by a boiler inspector without the permission of the Chief Inspector.
Read the Heating Plants and Power Plants on the Province's website ↗
Made under Boiler and Pressure Vessel Act, 2011, c.122.