Construction Prompt Payment and Adjudication Act, 2023, c.15
Section 3
Project agreements between the Crown or a local government and a special purpose entity
Cite as Construction Prompt Payment and Adjudication Act, 2023, c.15, s. 3 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Subject to this section and the regulations, this Act and the regulations apply with the necessary modifications if the Crown or a local government, as the owner, enters into a project agreement with a special purpose entity that requires the entity to finance and undertake an improvement on behalf of the Crown or local government, as the case may be, and, for that purpose, to enter into an agreement with a contractor in respect of the improvement.
(2) The special purpose entity is deemed to be the owner in place of the Crown or a local government, and the agreement between the special purpose entity and the contractor is deemed to be the contract for the purposes of this Act and the regulations.
(3) Subsection 8(1) does not apply to a project agreement referred to in subsection (1), and nothing in Part 2 prevents the inclusion of a provision in the project agreement that makes the giving of a proper invoice conditional on the prior certification of a payment certifier or on the special purpose entity’s prior approval.
(4) Part 2 does not apply to
(a) any portion of a project agreement entered into between the Crown or a local government, as the owner, and a special purpose entity that requires the entity to operate or maintain an improvement on behalf of the Crown or local government, or
(b) any contract or subcontract under a portion of a project agreement referred to in paragraph (a).
Read the Construction Prompt Payment and Adjudication Act on the Province's website ↗