Construction Services, N.B. Reg. 2022-78
Section 80
Refusal to enter into procurement contract
Cite as Construction Services, N.B. Reg. 2022-78, s. 80 · current to June 6, 2025 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
If the successful contractor refuses to enter into the procurement contract within 14 days after the procuring entity notifies the successful contractor under section 120 that it has been selected as the successful contractor, the procuring entity may
(a) cash or negotiate the bid security deposit and retain a sum equal to the difference between the value of the bid submission and the value of the next lowest bid submission and shall return an amount equal to the surplus, if any, to the contractor whose bid security deposit was forfeited, or
(b) notify the surety company if a bid bond was submitted.
Read the Construction Services on the Province's website ↗
Made under Procurement Act, 2012, c.20.