Guilty verdict during performance of procurement contract
Cite as Construction Services, N.B. Reg. 2022-78, s. 56 · current to June 6, 2025 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) If a contractor is found guilty of an offence referred to in section 55, the head of a Schedule 2 entity or the person responsible for its procurement shall cancel any existing procurement contract that contractor has with the Schedule 2 entity unless it would be too costly for or otherwise detrimental to the Schedule 2 entity.
(2) If a procurement contract is not cancelled under subsection (1), the head of the Schedule 2 entity or the person responsible for its procurement may take any measure that the head of the Schedule 2 entity or the person considers appropriate, including
(a) inspections,
(b) measures to prevent delays, and
(c) close tracking of the different stages or aspects of the contract.