Construction Remedies Act, 2020, c.29
Section 80
Priority of liens
Cite as Construction Remedies Act, 2020, c.29, s. 80 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) A lien has priority over
(a) all judgments, executions, assignments and receiving orders recovered, issued or made after the lien arises, and
(b) subject to subsection (2), all claims under conveyances, mortgages and other charges, and agreements for sale of land made by the owner before or after the lien arises.
(2) If a conveyance, mortgage, other charge or agreement for sale is registered in the appropriate land registration office before the registration of a claim for lien, any payment or advance made because of that conveyance, mortgage, charge or agreement has priority over a lien if it is made before the registration of a claim for lien or before notice of the lien has been given in writing to the person making the payment or advance, but has priority only to the extent that the total of all payments or advances made by the person, including that specific payment or advance, does not exceed the value of the land at the time the payment or advance is made.
(3) A notice under subsection (2) shall be in the form prescribed by regulation.
(4) If an owner has an estate or interest in land as purchaser under an agreement for sale and the purchase money or part of the purchase money is unpaid, the vendor has priority over a lien only to the extent of the value of the land at the time the lien arose.