Construction Remedies Act, 2020, c.29

Section 8

Completion of contract

Cite as Construction Remedies Act, 2020, c.29, s. 8 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

For the purposes of this Act, a contract is completed when the cost of completing it, correcting a known defect or supplying the services or materials remaining to be supplied for the improvement is not more than 1% of the contract price.