Construction Remedies Act, 2020, c.29
Section 61
Time for registering claim for lien – worker
Cite as Construction Remedies Act, 2020, c.29, s. 61 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) A worker may register a claim for lien for wages owing to the worker for the supply of services any time after the lien arises until the expiry of 60 days after the occurrence of the earliest of the following:
(a) a certificate of substantial performance is signed or a declaration of substantial performance is made in respect of the contract;
(b) the contract is completed, abandoned or terminated;
(c) the worker last supplies services for the improvement; and
(d) a certificate of completion of subcontract is signed or a declaration of completion of subcontract is made in respect of the subcontract under or in respect of which the worker supplied services.
(2) If a contract has been certified or declared to be substantially performed and the owner, contractor or a subcontractor proceeds to complete it, a worker may register a claim for lien for wages owing to the worker for services supplied to complete the substantially performed contract any time after the lien arises until the expiry of 60 days after the occurrence of the earliest of the following:
(a) the contract is completed, abandoned or terminated;
(b) the worker last supplies services for the improvement; and
(c) a certificate of completion of subcontract is signed or a declaration of completion of subcontract is made in respect of a subcontract under or in respect of which the worker supplied services.