Construction Remedies Act, 2020, c.29
Section 41
Certificate or declaration of substantial performance of contract
Cite as Construction Remedies Act, 2020, c.29, s. 41 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) If there is a payment certifier in respect of a contract, at the request of the contractor, the payment certifier shall determine whether the contract has been substantially performed, and if so determined the payment certifier shall certify the substantial performance of the contract by signing a certificate of substantial performance.
(2) A payment certifier shall sign a certificate of substantial performance within seven days after a request is made under subsection (1) or after the payment certifier determines that the contract has been substantially performed, whichever is later.
(3) If there is no payment certifier in respect of a contract, at the request of the contractor, the owner and contractor shall jointly determine whether the contract has been substantially performed, and if so determined they shall certify the substantial performance of the contract by signing a certificate of substantial performance.
(4) A contractor and owner shall both sign a certificate of substantial performance within seven days after a request is made under subsection (3) or after they determine that the contract has been substantially performed, whichever is later.
(5) A contractor shall request a determination under subsection (1) or (3), as the case may be, if requested by a subcontractor.
(6) A payment certifier or an owner and a contractor jointly, as the case may be, shall set out in a certificate of substantial performance the date the contract was substantially performed.
(7) Despite subsection (6), the date a certificate of substantial performance is signed shall be deemed, for the purposes of this Act, to be the date that the contract was substantially performed.
(8) A payment certifier shall give a copy of a certificate of substantial performance to the owner and to the contractor within three days after the certificate is signed.
(9) Within seven days after receiving a copy of a certificate of substantial performance, or after signing a certificate with an owner, as the case may be, a contractor shall
(a) post a copy of the certificate, or cause a copy to be posted,
(i) at the office at the site of the improvement, if there is one, otherwise, in a prominent place at the site of the improvement, or
(ii) on a website maintained by or on behalf of the owner if the following requirements are met:
(A) all lienholders in respect of the improvement are given the website address and any other information required to view the posted certificate; and
(B) no fees are charged for posting certificates, searching the website or viewing the posted certificates, and
(b) if the regulations provide for any additional manner of publication, publish the certificate in accordance with the regulations.
(10) If there is a failure or refusal to certify the substantial performance of a contract within a reasonable time, any person may apply to the court, and the court, on being satisfied that the contract has been substantially performed, and on any terms as to costs or otherwise that it considers appropriate, may declare that the contract has been substantially performed.
(11) A declaration of substantial performance shall contain the information set out in paragraphs 42(a) to (h) and, unless the court orders otherwise, the date the declaration is made shall be deemed, for the purposes of this Act, to be the date the contract was substantially performed.
(12) If a person who makes an application referred to in subsection (10) is not the contractor, that person shall provide the contractor with a copy of the declaration of substantial performance within seven days after receiving it from the court.
(13) Within four days after receiving a copy of a declaration of substantial performance, a contractor shall
(a) post a copy of the declaration, or cause a copy to be posted,
(i) at the office at the site of the improvement, if there is one, otherwise, in a prominent place at the site of the improvement, or
(ii) on a website maintained by or on behalf of the owner if the following requirements are met:
(A) all lienholders in respect of the improvement are given the website address and any other information required to view the posted declaration; and
(B) no fees are charged for posting declarations, searching the website or viewing the posted declarations, and
(b) if the regulations provide for any additional manner of publication, publish the declaration in accordance with the regulations.