Construction Remedies Act, 2020, c.29
Section 39
Methods of retaining holdbacks
Cite as Construction Remedies Act, 2020, c.29, s. 39 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
An owner may retain some or all of the amount required to be retained as a holdback using one or more of the following:
(a) an irrevocable standby letter of credit in the form prescribed by regulation;
(b) a holdback release bond in the form prescribed by regulation; and
(c) any other method prescribed by regulation.