Construction Remedies Act, 2020, c.29
Section 36
Holdback funds not to be applied to remedy default
Cite as Construction Remedies Act, 2020, c.29, s. 36 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
If a contractor or a subcontractor defaults in the performance of a contract or subcontract, as the case may be, a holdback shall not be applied by any owner toward obtaining services or materials in substitution for those that were to have been supplied by the person in default, nor in payment or satisfaction of any claim against the person in default, until all liens that may be claimed against that holdback have been extinguished, discharged or otherwise provided for under this Act.
Read the Construction Remedies Act on the Province's website ↗