Construction Remedies Act, 2020, c.29

Section 3

Interpretation of “direct costs”

Cite as Construction Remedies Act, 2020, c.29, s. 3 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

For the purposes of paragraph (b) of the definitions “contract price” and “subcontract price” in section 1, the direct costs incurred are the reasonable costs incurred in performing the contract or subcontract during the extended period, and include costs related to the supply of additional services or materials, additional insurance and surety bond premiums, and costs resulting from seasonal conditions, that, but for the extension, would not have been incurred, but do not include indirect damages suffered as a result of the extension.