Construction Remedies Act, 2020, c.29

Section 24

No claim for lien below amount prescribed by regulation

Cite as Construction Remedies Act, 2020, c.29, s. 24 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) No claim for lien shall be registered in respect of a lien that attaches to land and an improvement, if the amount of the claim or the aggregate of joined claims is less than the amount prescribed by regulation. (2) No claim for lien shall be given in respect of a lien against a public owner’s holdback, if the amount of the claim or the aggregate of joined claims is less than the amount prescribed by regulation.