Construction Remedies Act, 2020, c.29
Section 100
Costs
Cite as Construction Remedies Act, 2020, c.29, s. 100 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Subject to subsection (3), any order as to the costs of an action, application, motion or of any step in a proceeding under this Act is in the discretion of the court, and an order as to costs may be made against
(a) a party, or
(b) a person who represented a party, if the person
(i) knowingly participated in the registration or giving of a claim for lien, the registration of a certificate of pending litigation or the commencement of an action to enforce a lien,
(ii) represented a party at the trial of an action, where it was clear that the claim for lien was without foundation, was frivolous, vexatious or an abuse of process or was for an exaggerated amount, or that the lien had been extinguished, or
(iii) prejudiced or delayed the conduct of the action.
(2) An order under subsection (1) may be made on a solicitor and client basis.
(3) If the least expensive course is not taken by a party, the costs allowed to the party shall not exceed what would have been incurred had the least expensive course been taken.
(4) When a claim for lien is discharged under this Act or when judgment is given in favour of or against a claim for lien, the court may allow a reasonable amount for the costs of drawing and registering the claim for lien or for discharging the registration of the claim for lien.