Pre-tested pipe

Cite as Pipeline, N.B. Reg. 2006-2, s. 25 · current to December 18, 2020 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

If pre-tested pipe assemblies or segments are installed in a pipeline, the number of welds in the installations or segments that are not subjected to a pressure test shall be minimized to the extent that is practicable.
Read the Pipeline on the Province's website ↗

Made under Pipeline Act, 2005, c. P-8.5.