Vancouver Charter, SBC 1953, c. 55
Section 561B
Latecomer charges and cost recovery for excess or extended services
Cite as Vancouver Charter, SBC 1953, c. 55, s. 561B · read from BC Laws on November 17, 2026
The text
(1) For the purposes of this section, “latecomer charge” means a charge under subsection (2) (c).
(2) If the owner is required under section 561A (3) (b) to pay all or part of the costs of excess or extended services, the city must
(a) determine the proportion of the cost of providing the street or water, sewage or drainage facilities that it considers constitutes the excess or extended services,
(b) determine which part of the excess or extended services that it considers will benefit each of the parcels of land that will be served by the excess or extended services, and
(c) impose, as a condition of an owner connecting to or using the excess or extended services, a charge related to the benefit determined under paragraph (b).
(3) If the owner pays all or part of the costs of excess or extended services, the city must pay the owner
(a) all the latecomer charges collected under subsection (2) (c), if the owner pays all the costs, or
(b) a corresponding proportion of all latecomer charges collected, if the owner pays a portion of the costs.
(4) If the city pays all or part of the costs of excess or extended services, it may recover costs
(a) by a latecomer charge under subsection (2) (c), or
(b) by a tax imposed in accordance with Part XXIV [Local Improvements], other than section 506 [process for initiating local improvements].
(5) A latecomer charge must include interest calculated annually at a rate established by bylaw, payable for the period beginning when the excess or extended services were completed, up to the date that the connection is made or the use begins.
(6) Subject to subsection (7), latecomer charges must be collected during the period beginning when the excess or extended services are completed, up to
(a) a date to be agreed on by the owner and the city, or
(b) if there is no agreement, a date determined under the Arbitration Act.
(7) No latecomer charges are payable beyond 15 years from the date the services are completed.
(8) If an owner, in accordance with a bylaw under section 292, provides a street or water, sewage or drainage facilities that serve land other than the land being subdivided or developed, this section applies.