Municipal Replotting Act, RSBC 2016, c. 1
Section 23
Compensation for loss, damage and costs
Cite as Municipal Replotting Act, RSBC 2016, c. 1, s. 23 · read from BC Laws on November 17, 2026
The text
(1) An owner who did not consent and who gives notice of complaint as provided in section 26 (2) (f) has the right to monetary compensation for the following:
(a) any loss of value of the former parcel insofar as adequate compensation is not provided by the new parcel allotted;
(b) any loss of or damage to buildings or other improvements on the former parcel;
(c) the cost of moving buildings or other improvements on the former parcel;
(d) any loss of income caused by the replotting scheme from
(i) the use of buildings, or
(ii) the special condition or use of the former parcel.
(2) In determining the amount of compensation,
(a) a former parcel must be valued at its market value at the time of the initiation of the replotting scheme, but an increase in its value caused by the anticipation or initiation of the scheme must not be taken into consideration, and
(b) a new parcel must be valued at its market value on completion of the replotting scheme.
(3) A person is not entitled to compensation for any of the following:
(a) costs, expenses, loss, damage or inconvenience
(i) incurred or sustained in investigating the replotting scheme proceeding,
(ii) incurred or sustained in presenting a complaint or making an appeal, or
(iii) caused by the initiation of, delay in or discontinuance of the replotting scheme;
(b) an actual or anticipated loss or inconvenience of access to new parcels or of use of a municipal or public utility or service if the loss or inconvenience is due to the new highways not being open for traffic;
(c) an actual or anticipated loss, damage or inconvenience suffered in common with all or the majority of other owners;
(d) a building or other structure constructed, erected, placed or altered after the initiation of the replotting scheme or an actual or anticipated loss, damage or expense incidental to the construction, erection, placement, alteration or removal of the building or other structure;
(e) an improvement made to land after the initiation of the replotting scheme or an actual or anticipated loss, damage or expense incidental to the improvement;
(f) a reduction in or loss of value due to reduction in area within the limits of a right to take land for highway purposes contained in the Crown grant of or statute applying to the land.