(1) On an application under section 540, the board of variance may order that a minor variance be permitted from the requirements of the applicable bylaw, or that the applicant be exempted from section 531 (1) [alteration or addition while non-conforming use continued], if the board of variance
(a) has heard the applicant and any person notified under section 541,
(b) finds that undue hardship would be caused to the applicant if the bylaw or section 531 (1) is complied with, and
(c) is of the opinion that the variance or exemption does not do any of the following:
(i) result in inappropriate development of the site;
(ii) adversely affect the natural environment;
(iii) substantially affect the use and enjoyment of adjacent land;
(iv) vary permitted uses and densities under the applicable bylaw;
(v) defeat the intent of the bylaw;
(vi) vary the application of an applicable bylaw in relation to residential rental tenure.
(2) The board of variance must not make an order under subsection (1) that would do any of the following:
(a) be in conflict with a covenant registered under section 219 of the Land Title Act or section 24A of the Land Registry Act, R.S.B.C. 1960, c. 208;
(b) deal with a matter that is covered in a land use permit or covered in a land use contract;
(c) deal with a matter that is covered by a phased development agreement under Division 12 [Phased Development Agreements];
(d) deal with a flood plain specification under section 524 (3);
(e) apply to a property
(i) for which an authorization for alterations is required under Part 15 [Heritage Conservation],
(ii) for which a heritage revitalization agreement under section 610 is in effect, or
(iii) that is scheduled under section 614 (3) (b) [protected heritage property] or contains a feature or characteristic identified under section 614 (3) (c) [heritage value or character].
(3) In relation to an order under subsection (1),
(a) if the order sets a time within which the construction of the building, structure or manufactured home park must be completed and the construction is not completed within that time, or
(b) if that construction is not substantially started within 2 years after the order was made, or within a longer or shorter time period established by the order,
the permission or exemption terminates and the bylaw or section 531 (1), as the case may be, applies.
(4) A decision of the board of variance under subsection (1) is final.