Local Government Act, RSBC 2015, c. 1
Section 463
Withholding building permits and business licences that conflict with bylaws in preparation
Cite as Local Government Act, RSBC 2015, c. 1, s. 463 · read from BC Laws on November 17, 2026
The text
(1) A local government may direct that a building permit be withheld for a period of 30 days, beginning on the day the application for the permit was made, if it passes a resolution identifying what it considers to be a conflict between a development proposed in the application for a building permit and
(a) an official community plan that is under preparation, or
(b) a bylaw, under any of the following, that is under preparation:
(i) Division 5 [Zoning Bylaws];
(ii) Division 12 [Phased Development Agreements];
(iii) section 523 [runoff control requirements];
(iv) section 524 [requirements in relation to flood plain areas];
(v) section 525 [off-street parking and loading space requirements].
(2) Subsection (1) does not apply unless a local government has, by resolution at least 7 days before the application for a building permit, begun the preparation of a plan or bylaw that is in conflict with the application.
(3) During the 30 day period referred to in subsection (1), the local government must consider the application for the permit and may
(a) direct the permit be withheld for a further 60 days, or
(b) grant the permit, but impose conditions in it that would be in the public interest, having regard to the plan or bylaw that is under preparation.
(4) If the local government does not adopt a plan or bylaw referred to in subsection (1) within the 60 day period, the owners of the land for which a building permit was withheld under this section are entitled to compensation for damages arising from the withholding of the building permit.
(5) For the purposes of subsection (4),
(a) Division 7 [Expropriation and Compensation] of Part 8 [Regional Districts: General Powers and Responsibilities] of this Act applies in relation to a regional district, and
(b) Division 4 [Expropriation and Compensation] of Part 3 [Additional Powers and Limits on Powers] of the Community Charter applies in relation to a municipality.
(6) In relation to land that is subject to a resolution under subsection (1), the council may direct that a business licence in respect of the same land be withheld for a period not longer than 90 days, if the council considers that the use to which the land would be put and to which the business licence application relates would be contrary to the use that would be permitted by the bylaw that is under preparation.
(7) Any requirement to approve a permit or licence under this section is subject to section 557 [Environmental Management Act requirements].
Read the Local Government Act on BC Laws ↗