Section 236

Delay in proceeding

Cite as Strata Property Act, SBC 1998, c. 43, s. 236 · read from BC Laws on November 17, 2026

The text

(1) On application by the strata corporation, the Supreme Court may order that the owner developer complete a phase by a set date if (a) the owner developer has elected to proceed, or is deemed to have elected to proceed under section 231, and (b) the court is satisfied that the owner developer has not proceeded with the phase (i) within a reasonable time after the date stated in the Phased Strata Plan Declaration or an amended declaration, or (ii) at a reasonable speed. (2) If the owner developer does not comply with the court order under subsection (1), the court may declare that the owner developer be deemed to have elected not to proceed.