Builders Lien Act, SBC 1997, c. 45
Section 41
Right to information
Cite as Builders Lien Act, SBC 1997, c. 45, s. 41 · read from BC Laws on November 17, 2026
The text
(1) A lien holder or a beneficiary of a trust under this Act may, at any time, by delivering a written request, require
(a) from the owner
(i) the terms of the head contract or contract under which the lien holder of beneficiary claims, including the names of the parties to the contract, the contract price and the state of accounts between the owner and the head contractor,
(ii) the name and address of the savings institution in which a holdback account has been opened, and the account number,
(iii) particulars of credits to and payments from the holdback account, including the dates of credits and payments, and the balance at the time the information is given, and
(iv) particulars of any labour and material payment bond posted by the contractor with the owner in respect of the head contract or contract under which the lien holder or beneficiary claims, and
(b) from a mortgagee or an unpaid vendor
(i) the terms of the mortgage or agreement for sale,
(ii) in the case of a mortgage, particulars of the amount advanced under the mortgage, including the dates of advances, and of any arrears in payment, and
(iii) in the case of an agreement for sale, particulars of the amount secured under the agreement for sale and any arrears in payment.
(2) The owner may request in writing from
(a) a subcontractor when a claim of lien has been filed or a written notice of a claim of lien has been received by the owner, and
(b) the contractor, at any time,
the following information:
(c) the terms of any subcontract, including the names of the parties to the subcontract, the subcontract price and the state of accounts between the contractor and a subcontractor or between a subcontractor and another subcontractor, or any other person providing work or material;
(d) particulars of any labour and material payment bond posted by a subcontractor with the contractor or by a subcontractor with another subcontractor.
(3) The person to whom a request is made under subsection (1) or (2) must comply within 10 days after the day the request is delivered.
(4) A person who fails to comply in writing with a request within the time provided in subsection (3), or who knowingly or negligently misstates the information requested, is liable to the person requesting the information for any resulting loss or damage.
(5) On the failure of a person to comply with a request made under subsection (2) within the time provided, the owner may also, if the request is made of
(a) a contractor, withhold further payments to the contractor, or
(b) a subcontractor, instruct the contractor or another subcontractor to withhold further payments to the subcontractor
until the contractor or subcontractor, as the case may be, has complied with the request.
(6) The court may, on application by an interested person at any time before or after an action is commenced for the enforcement of a claim of lien,
(a) order that the owner, mortgagee, vendor, contractor or subcontractor produce for inspection all contracts, subcontracts, documents, books or records relating to the contract or subcontract or to the payment of the contract or subcontract price,
(b) order that any person referred to in paragraph (a) deliver to the applicant copies of any documents referred to in that paragraph, and
(c) make an order as to the costs of the application.