The text

(1) The portion of the proceeds of sale allocated under section 36 (2) (b) must be applied to pay the claims of lien of contractors and workers engaged by the owner, and to pay the owner, and distributed according to the following priority: (a) the costs of lien claimants of and incidental to the proceedings of filing and enforcing their claims of lien; (b) up to 6 weeks' wages, if that much is owed, to workers; (c) the amount of money owed (i) to the workers in excess of 6 weeks' wages, and (ii) to the contractors; (d) the owner. (2) The funds available to the members of a category of lien claimants constituted under each of subsection (1) (a), (b) or (c) must be distributed proportionally among the members of that category so that a single member of the category is entitled to that proportion of the amount recovered that the amount of the member's lien bears to the aggregate amount of the liens of all members of the category, but a lien claimant is not entitled to recover more than the amount of the claimant's lien and entitlement to costs under subsection (1) (a). (3) Money distributed under this section is subject to sections 10, 11 and 14.
Read the Builders Lien Act on BC Laws ↗