Utilities Commission Act, RSBC 1996, c. 473

Section 85

Hearings to be held in certain cases

Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 85 · read from BC Laws on November 17, 2026

The text

(1) Except in case of urgency, of which the commission is sole judge, the commission must not, without a hearing, make an order involving an outlay, loss or deprivation to a public utility. (2) If an order is made in case of urgency without a hearing, on the application of a person interested, the commission must as soon as practicable hear and reconsider the matter and make any further order it considers advisable.
Read the Utilities Commission Act on BC Laws ↗