Utilities Commission Act, RSBC 1996, c. 473
Section 71
Energy supply contracts
Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 71 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (1.1), a person who, after this section comes into force, enters into an energy supply contract must
(a) file a copy of the contract with the commission under rules and within the time it specifies, and
(b) provide to the commission any information it considers necessary to determine whether the contract is in the public interest.
(1.1) Subsection (1) does not apply to an energy supply contract for the sale of natural gas unless the sale is to a public utility.
(2) The commission may make an order under subsection (3) if the commission, after a hearing, determines that an energy supply contract to which subsection (1) applies is not in the public interest.
(2.1) In determining under subsection (2) whether an energy supply contract filed by a public utility other than the authority is in the public interest, the commission must consider
(a) the applicable of British Columbia's energy objectives,
(b) the most recent long-term resource plan filed by the public utility under section 44.1, if any,
(c) the extent to which the energy supply contract is consistent with the applicable requirements under sections 6 and 19 of the Clean Energy Act,
(d) the interests of persons in British Columbia who receive or may receive service from the public utility,
(e) the quantity of the energy to be supplied under the contract,
(f) the availability of supplies of the energy referred to in paragraph (e),
(g) the price and availability of any other form of energy that could be used instead of the energy referred to in paragraph (e), and
(h) in the case only of an energy supply contract that is entered into by a public utility, the price of the energy referred to in paragraph (e).
(2.2) Subsection (2.1) (a) to (c) does not apply if the commission considers that the matters addressed in the energy supply contract filed under subsection (1) were determined to be in the public interest in the course of considering a long-term resource plan under section 44.1.
(2.21) In determining under subsection (2) whether an energy supply contract filed by the authority is in the public interest, the commission, in addition to considering the interests of persons in British Columbia who receive or may receive service from the authority, must consider
(a) British Columbia's energy objectives,
(b) the most recent of the following documents:
(i) an integrated resource plan approved under section 4 of the Clean Energy Act before the repeal of that section;
(ii) a long-term resource plan filed by the authority under section 44.1 of this Act,
(c) the extent to which the energy supply contract is consistent with the requirements under section 19 of the Clean Energy Act,
(d) the quantity of the energy to be supplied under the contract,
(e) the availability of supplies of the energy referred to in paragraph (d),
(f) the price and availability of any other form of energy that could be used instead of the energy referred to in paragraph (d), and
(g) in the case only of an energy supply contract that is entered into by a public utility, the price of the energy referred to in paragraph (d).
(2.22) Subsection (2.21) (a) to (c) does not apply if the commission considers that the matters addressed in the energy supply contract filed by the authority under subsection (1) were determined to be in the public interest in the course of considering a long-term resource plan under section 44.1.
(2.3) A public utility may submit to the commission a proposed energy supply contract setting out the terms and conditions of the contract and a process the public utility intends to use to acquire power from other persons in accordance with those terms and conditions.
(2.4) If satisfied that it is in the public interest to do so, the commission, by order, may approve a proposed contract submitted under subsection (2.3) and a process referred to in that subsection.
(2.5) In considering the public interest under subsection (2.4) with respect to a submission by a public utility other than the authority, the commission must consider
(a) the applicable of British Columbia's energy objectives,
(b) the most recent long-term resource plan filed by the public utility under section 44.1,
(c) the extent to which the application for the proposed contract is consistent with the applicable requirements under sections 6 and 19 of the Clean Energy Act, and
(d) the interests of persons in British Columbia who receive or may receive service from the public utility.
(2.51) In considering the public interest under subsection (2.4) with respect to a submission by the authority, the commission, in addition to considering the interests of persons in British Columbia who receive or may receive service from the authority, must consider
(a) British Columbia's energy objectives,
(b) the most recent of the following documents:
(i) an integrated resource plan approved under section 4 of the Clean Energy Act before the repeal of that section;
(ii) a long-term resource plan filed by the authority under section 44.1 of this Act, and
(c) the extent to which the application for the proposed contract is consistent with the requirements under section 19 of the Clean Energy Act.
(2.6) If the commission issues an order under subsection (2.4), the commission may not issue an order under subsection (3) with respect to a contract
(a) entered into exclusively on the terms and conditions, and
(b) as a result of the process
referred to in subsection (2.3).
(3) If subsection (2) applies, the commission may
(a) by order, declare the contract unenforceable, either wholly or to the extent the commission considers proper, and the contract is then unenforceable to the extent specified, or
(b) make any other order it considers advisable in the circumstances.
(4) If an energy supply contract is, under subsection (3) (a), declared unenforceable either wholly or in part, the commission may order that rights accrued before the date of the order under that subsection be preserved, and those rights may then be enforced as fully as if no proceedings had been taken under this section.
(5) An energy supply contract or other information filed with the commission under this section must be made available to the public unless the commission considers that disclosure is not in the public interest.
Read the Utilities Commission Act on BC Laws ↗