Utilities Commission Act, RSBC 1996, c. 473
Section 44.1
Long-term resource and conservation planning
Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 44.1 · read from BC Laws on November 17, 2026
The text
(1) [Repealed 2010-22-65.]
(2) Subject to subsection (2.1), a public utility must file with the commission, in the form and at the times the commission requires, a long-term resource plan including all of the following:
(a) an estimate of the demand for energy the public utility would expect to serve if the public utility does not take new demand-side measures during the period addressed by the plan;
(b) a plan of how the public utility intends to reduce the demand referred to in paragraph (a) by taking cost-effective demand-side measures;
(c) an estimate of the demand for energy that the public utility expects to serve after it has taken cost-effective demand-side measures;
(d) a description of the facilities that the public utility intends to construct or extend in order to serve the estimated demand referred to in paragraph (c);
(e) information regarding the energy purchases from other persons that the public utility intends to make in order to serve the estimated demand referred to in paragraph (c);
(f) an explanation of why the demand for energy to be served by the facilities referred to in paragraph (d) and the purchases referred to in paragraph (e) are not planned to be replaced by demand-side measures;
(g) any other information required by the commission.
(2.1) The authority need not file a long-term resource plan before February 28, 2021.
(3) The commission may exempt a public utility from the requirement to include in a long-term resource plan filed under subsection (2) any of the information referred to in paragraphs (a) to (f) of that subsection if the commission is satisfied that the information is not applicable with respect to the nature of the service provided by the public utility.
(4) [Repealed 2010-22-65.]
(5) The commission may establish a process to review long-term resource plans filed under subsection (2).
(6) After reviewing a long-term resource plan filed under subsection (2), the commission must
(a) accept the plan, if the commission determines that carrying out the plan would be in the public interest, or
(b) reject the plan.
(7) The commission may accept or reject, under subsection (6), a part of a public utility's plan, and, if the commission rejects a part of a plan,
(a) the public utility may resubmit the part within a time specified by the commission, and
(b) the commission may accept or reject, under subsection (6), the part resubmitted under paragraph (a) of this subsection.
(8) In determining under subsection (6) whether to accept a long-term resource plan, the commission must consider
(a) the applicable of British Columbia's energy objectives,
(b) the extent to which the plan is consistent with the applicable requirements under sections 6 and 19 of the Clean Energy Act,
(c) whether the plan shows that the public utility intends to pursue adequate, cost-effective demand-side measures, and
(d) the interests of persons in British Columbia who receive or may receive service from the public utility.
(9) In accepting under subsection (6) a long-term resource plan, or part of a plan, the commission may do one or both of the following:
(a) order that a proposed utility plant or system, or extension of either, referred to in the accepted plan or the part is exempt from the operation of section 45 (1);
(b) order that, despite section 75, a matter the commission considers to be adequately addressed in the accepted plan or the part is to be considered as conclusively determined for the purposes of any hearing or proceeding to be conducted by the commission under this Act, other than a hearing or proceeding for the purposes of section 99.
Read the Utilities Commission Act on BC Laws ↗