The text

If the commission, after a hearing, determines that (a) an extension of the existing services of a public utility, in a general area that the public utility may properly be considered responsible for developing, is feasible and required in the public interest, and (b) the construction and maintenance of the extension will not necessitate a substantial increase in rates chargeable, or a decrease in services provided, by the utility elsewhere, the commission may order the utility to make the extension on terms the commission directs, which may include payment of all or part of the cost by the persons affected.