Utilities Commission Act, RSBC 1996, c. 473

Section 28

Utility must provide service if supply line near

Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 28 · read from BC Laws on November 17, 2026

The text

(1) On being requested by the owner or occupier of the premises to do so, a public utility must supply its service to premises that are located within 200 metres of its supply line or any lesser distance that the commission prescribes suitable for that purpose. (2) Before supplying the service under subsection (1) or making a connection for the purpose, or as a condition of continuing to supply the service, the public utility may require the owner or occupier to give reasonable security for repayment of the costs of making the connection as set out in the filed schedule of rates. (2.1) If required to do so by regulation, the commission, in accordance with the prescribed requirements, must set a rate for the authority respecting the service provided under subsection (1). (2.2) A requirement prescribed for the purposes of subsection (2.1) applies despite (a) any other provision of this Act or any regulation under this Act, except for a regulation under section 3, or (b) any previous decision of the commission. (3) After a hearing and for proper cause, the commission may relieve a public utility from the obligation to supply service under this Act on terms the commission considers proper and in the public interest.
Read the Utilities Commission Act on BC Laws ↗