Expropriation Act, RSBC 1996, c. 125

Section 18

Decision of approving authority

Cite as Expropriation Act, RSBC 1996, c. 125, s. 18 · read from BC Laws on November 17, 2026

The text

(1) After considering the report submitted under section 17, the approving authority must approve, approve with modifications or reject the expropriation, but an expropriation must not be modified so as to affect land of a person who was not a participant in the inquiry. (2) If (a) an inquiry is not requested or has been refused, or (b) an owner is not, under section 10 (2), entitled to request an inquiry, the approving authority must (c) approve the expropriation, and (d) notify the expropriating authority and each owner of the approval in writing. (3) If an inquiry was held, the approving authority must, not later than 30 days after receiving the report submitted under section 17, serve the approving authority's decision, with written reasons, on every participant and every owner of the land expropriated. (4) If a request for an inquiry is withdrawn, the approving authority may proceed as though the request had not been made. (5) If the approving authority modifies the expropriation under subsection (1), the expropriating authority must (a) file in the land title office an amended expropriation notice in accordance with the modification, and section 6 (4) applies, and (b) notify each owner of the modified approval in writing and accompany the notice with a copy of the amended expropriation notice. (6) If the approving authority rejects the expropriation, (a) the expropriating authority must file in the land title office a notice of cancellation in the prescribed form, and (b) on receiving the notice of cancellation, the registrar must cancel the expropriation notice filed and endorsed under section 7 (1).
Read the Expropriation Act on BC Laws ↗