Renewable Energy Projects (Streamlined Permitting) Regulation, B.C. Reg. 93/2025
Section 7
Direction in relation to formerly reviewable wind energy projects
Cite as Renewable Energy Projects (Streamlined Permitting) Regulation, B.C. Reg. 93/2025, s. 7 · last amended July 10, 2026 · read from BC Laws on November 17, 2026
The text
(1) In this section:
“formerly reviewable wind energy project” means any of the following that is not a reviewable project within the meaning of the Environmental Assessment Act:
(a) a land-based wind energy project with 15 or more turbines;
(b) a wind energy project with a rated nameplate capacity equal to or greater than 50 MW;
“participation provisions” means
(a) sections 22.3.1 and 22.3.2 of the final agreement of the Maa-nulth First Nations,
(b) paragraphs 3 and 4 of Chapter 13 of the final agreement of the Tla'amin Nation, and
(c) clauses 7 and 8 of Chapter 15 of the final agreement of the Tsawwassen First Nation.
(2) If a permit for a formerly reviewable wind energy project locates an operating area on treaty lands of a treaty first nation, section 34 (2) (a) [required ownership, interest or authorization] of the primary Act applies in relation to the operating area and, for that purpose, is to be read as requiring that the permit holder either
(a) is the treaty first nation, or
(b) has acquired the consent of the treaty first nation for the energy resource activities permitted by the permit to be carried out in the operating area.
(3) The regulator is directed, for the purposes of section 25 (1.1) [permits and authorizations issued by regulator] of the primary Act, not to issue a permit for a formerly reviewable wind energy project unless the participation provisions have been upheld.
(4) For the purposes of subsection (3), the participation provisions are to be read as though
(a) a reference to a Provincial Project were a reference to a formerly reviewable wind energy project, and
(b) a reference to participation in an assessment of environmental effects were a reference to participation in the process by which the regulator
(i) assesses the environmental effects of a formerly reviewable wind energy project, and
(ii) determines under section 25 of the primary Act whether to issue a permit and what conditions are to be imposed on the permit.
Read the Renewable Energy Projects (Streamlined Permitting) Regulation on BC Laws ↗
Made under Renewable Energy Projects (Streamlined Permitting) Act, SBC 2025, c. 12.