Code of Practice for Agricultural Environmental Management, B.C. Reg. 8/2019
Section 24
Earthen storage basins
Cite as Code of Practice for Agricultural Environmental Management, B.C. Reg. 8/2019, s. 24 · last amended July 15, 2029 · read from BC Laws on November 17, 2026
The text
Despite section 23 (1) [permanent storage in vulnerable aquifer recharge areas], a person who began, before February 28, 2019, to store liquid manure in an earthen basin dug into the ground in a vulnerable aquifer recharge area must do all of the following:
(a) have a qualified professional assess the storage basin for leaks of stored materials
(i) before February 28, 2021, and
(ii) until a protective base is installed, at least every 5 years after the last assessment or more often if the qualified professional believes it to be necessary;
(b) if any leaks are found on assessment under paragraph (a),
(i) take immediate corrective action to stop the leaks and to prevent further leaks, and
(ii) take steps as soon as reasonably practicable to install a protective base on the bottom and sides of the storage basin;
(c) keep a record of
(i) the date and results of each assessment conducted under paragraph (a), and
(ii) all actions taken under paragraph (b), if any;
(d) whether or not any leaks are found on assessment under paragraph (a), have a protective base on the bottom and sides of the storage basin before February 28, 2029, or an earlier date required by a director.
Read the Code of Practice for Agricultural Environmental Management on BC Laws ↗
Made under Environmental Management Act, SBC 2003, c. 53.