Energy Resource Road Regulation, B.C. Reg. 56/2013

Section 6

Bridges and culverts

Cite as Energy Resource Road Regulation, B.C. Reg. 56/2013, s. 6 · last amended September 1, 2023 · read from BC Laws on November 17, 2026

The text

(1) Subject to subsections (2) to (4), a road permit holder may not construct or install a bridge or culvert on an energy resource road unless all of the applicable following requirements are met: (a) the bridge is designed, fabricated and installed in compliance with (i) the Canadian Highway Bridge Design Code, CAN/CSA-S6, of the Canadian Standards Association, and (ii) soil properties standards, as they apply to bridge piers and abutments, set out in the Canadian Foundation Engineering Manual; (b) the culvert is designed and fabricated (i) in compliance with whichever of the following, as amended from time to time, is applicable: (A) Canadian Standards Association standard CAN/CSA G401, Corrugated Steel Pipe Products; (B) section B182.8 of Canadian Standards Association standard CSA B1800, Plastic Nonpressure Pipe Compendium, or (ii) so that it is as strong as a culvert designed and fabricated in accordance with subparagraph (i); (c) the bridge, if it will cross a stream or a fish stream, or the culvert, if it will be in a stream or a fish stream, is designed to pass the highest peak flow of the stream that can reasonably be expected within the return periods set out in column 2 of the following table for the period the road permit holder anticipates the bridge or culvert will remain on the site, as set out opposite in column 1 of the table: Column 1 Anticipated period bridge or culvert will remain on site Column 2 Peak flow period bridge or culvert, 3 years or less 10 years bridge other than a bridge within a community watershed, more than 3 years but less than 15 years 50 years bridge within a community watershed, more than 3 years 100 years bridge, 15 years or more 100 years culvert, more than 3 years 100 years (2) A road permit holder may construct or install a bridge that does not comply with subsection (1) (c) if (a) the bridge is designed to pass expected flows during the period the bridge is anticipated to remain on the site, and (b) the construction, installation and use of the bridge occurs during a period of low flow. (c) Repealed. [B.C. Reg. 216/2020, s. 7 (c).] (3) A road permit holder may construct or install a culvert that does not comply with subsection (1) (c) if (a) the installation is temporary and the person does not expect to subsequently install a replacement culvert at that location, (b) the stream in which the culvert is being installed is not a fish stream, (c) the culvert will pass the flow that will occur during the period the culvert remains on the site, and (d) the installation of the culvert occurs during a period of low flow. (e) Repealed. [B.C. Reg. 216/2020, s. 7 (d).] (3.1) A road permit holder must remove the following structures from the energy resource road before any period of high flow begins: (a) a bridge referred to in subsection (2), or the components of the bridge that are vulnerable to damage by high flow; (b) a culvert referred to in subsection (3). (4) A road permit holder may construct or install a bridge barrier that does not comply with subsection (1) (a) (i) if the bridge barrier's bridge (a) is intended primarily for industrial traffic and no pedestrian traffic, (b) is less than 5 m above water, (c) has good vertical and horizontal alignment, and (d) is designed to ensure the safety of permit holders.
Read the Energy Resource Road Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.