Energy Resource Road Regulation, B.C. Reg. 56/2013
Section 11
Report regarding construction
Cite as Energy Resource Road Regulation, B.C. Reg. 56/2013, s. 11 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
Within 60 days of completion of the construction of an energy resource road under a permit, the road permit holder must submit to the regulator a report, in the form and manner specified by the regulator, describing the location of the constructed road.
Read the Energy Resource Road Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.