Cite as Depreciation of Industrial and Electrical Power Generating Facility Improvements Regulation, B.C. Reg. 53/2016, s. 1 · last amended December 21, 2020 · read from BC Laws on November 17, 2026

The text

In this regulation: “Act” means the Assessment Act; “chronological age” means, (a) in relation to an industrial improvement or part of an industrial improvement that is part of a major industrial plant, the number of years determined by subtracting from the year in which the new assessment roll is completed whichever of the following years applies: (i) in the case of an industrial improvement or part of an industrial improvement that was constructed or installed before the plant commenced operation, the year in which the plant commenced operation; (ii) in the case of an industrial improvement or part of an industrial improvement that was constructed or installed after the plant commenced operation, the year in which the construction or installation of the industrial improvement or part of an industrial improvement was completed, and (b) in relation to an improvement or part of an improvement that is part of an electrical power generating facility, the number of years determined by subtracting from the year in which the new assessment roll is completed whichever of the following years applies: (i) in the case of an improvement or part of an improvement that was constructed or installed before the facility commenced operation, the year in which the facility commenced operation; (ii) in the case of an improvement or part of an improvement that was constructed or installed after the facility commenced operation, the year in which the construction or installation of the improvement or part of an improvement was completed; “dam” means a dam as defined in section 20.1 of the Act to which that section applies; “effective age”, in relation to an industrial improvement or an electrical power generating facility improvement, means the number of years determined by (a) calculating the total cost of the improvement, (b) multiplying the chronological age of each part of the improvement by the cost of that part to give the weighted age of that part, (c) adding the weighted ages of all of the parts of the improvement, and (d) dividing the sum of the weighted ages by the total cost of the improvement and rounding the quotient up to the next whole year to yield the effective age of the improvement; “electrical power generating facility” means a dam, a power plant or a substation; “electrical power generating facility improvement” means an improvement that is part of an electrical power generating facility; “industrial improvement” has the same meaning as in section 20 of the Act; “LNG improvement” means an industrial improvement that is part of a major LNG plant or is part of an industrial improvement that is part of a major LNG plant; “major industrial plant” means a plant designed and built for a purpose described in paragraphs (a) to (q) of the definition of "industrial improvement" in section 20 (1) of the Act; “major LNG plant” means a major industrial plant that is designed (a) to process natural gas, and (b) to produce at least 4 million tonnes of liquefied natural gas per year, and includes associated facilities used for the loading of liquefied natural gas onto sea going ships or barges and storage facilities that are ancillary to those loading facilities; “power plant” means a power plant as defined in section 20.1 of the Act to which that section applies; “substation” means a substation as defined in section 20.1 of the Act to which that section applies; “wind power plant” means a power plant that uses a wind turbine to generate or supply electricity from the wind.
Read the Depreciation of Industrial and Electrical Power Generating Facility Improvements Regulation on BC Laws ↗

Made under Assessment Act, RSBC 1996, c. 20.