Processing Facility Regulation, B.C. Reg. 48/2021
Section 16
Notice of operation
Cite as Processing Facility Regulation, B.C. Reg. 48/2021, s. 16 · last amended March 10, 2026 · read from BC Laws on November 17, 2026
The text
(1) Before operation of any part of a processing facility begins, a processing facility permit holder must complete all of the following steps, in order:
(a) give to the regulator the notice and records referred to in subsection (2);
(b) wait until either
(i) the regulator gives notice under subsection (3) (b), or
(ii) 14 days pass after the notice and records referred to in subsection (2) are given to the regulator, if no notice is given by the regulator under subsection (3) (a) or (b);
(c) give to the regulator the notice referred to in subsection (4).
(2) For the purposes of subsection (1) (a), the processing facility permit holder must give to the regulator all of the following:
(a) notice that the permit holder
(i) intends to begin operating the processing facility, and
(ii) has implemented the management system;
(b) Repealed. [B.C. Reg. 181/2022, App. 4, s. 1.]
(c) a list, completed by a qualified professional, of all safety critical devices at the processing facility.
(3) For the purposes of subsection (1) (b), the regulator may give one or both of the following notices to the processing facility permit holder:
(a) a notice that the regulator requires additional time to review the information given to the regulator under subsection (2) (b) and (c) and section 14 (2) [pre-operation testing];
(b) a notice that the permit holder may begin operation.
(4) For the purposes of subsection (1) (c), the processing facility permit holder must give at least 24 hours' notice to the regulator of the date that the permit holder intends to begin operating the processing facility.
Read the Processing Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.