(1) A processing facility permit holder must
(a) report to the regulator, in accordance with subsection (2), respecting any
(i) changes to the construction schedule, and
(ii) updates to the engineering design, and
(b) undertake risk assessments respecting any updates to the engineering design.
(2) Reports under subsection (1) must be made once every 6 months during the period that
(a) begins on the date the processing facility permit is issued, and
(b) ends on the earliest date that the processing facility permit holder sends notice to the regulator that the permit holder intends
(i) to begin operating the processing facility, or
(ii) to surrender the processing facility permit.
(3) In addition to the reports referred to in subsection (1) (a), if the engineering design is updated, a processing facility permit holder must do all of the following:
(a) give to the regulator an updated design basis for the systems referred to in section 3 (1) (e) [application for processing facility permit];
(b) ensure that a qualified professional completes an updated hazard identification study with respect to process hazards;
(c) if the qualified professional is of the opinion that it is necessary given the results under paragraph (b), ensure that a qualified professional completes a safety integrity level study, being a study of the extent to which risk reduction is required by the use of safety functions, including automatic instrument controls;
(d) give to the regulator a report that includes the findings and recommendations of the studies referred to in paragraph (b) and, if applicable, paragraph (c).
Read the Processing Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.