Direction No. 9 to the British Columbia Utilities Commission, B.C. Reg. 41/2025
Schedule 1
Appendix A
Cite as Direction No. 9 to the British Columbia Utilities Commission, B.C. Reg. 41/2025, Schedule 1 · last amended March 17, 2025 · read from BC Laws on November 17, 2026
The text
Appendix A OATT Rates Service Rate Schedule
in Authority's
Open Access
Transmission Tariff Rate effective
April 1, 2025 Rate effective
April 1, 2026 Network Integration Transmission Service 00 $88.117 million/month $90.586 million/month Long-Term Firm Point-to-Point Transmission Service 01 $92 207/MW/year $94 573/MW/year Monthly Short-Term Firm and Non-Firm Point-to-Point Transmission Service 01 $7 683.86/MW/month $7 881.04/MW/month Weekly Short-Term Firm and Non-Firm Point-to-Point Transmission Service 01 $1 773.21/MW/week $1 818.71/MW/week Daily Short-Term Firm and Non-Firm Point-to-Point Transmission Service 01 $252.62/MW/day $259.10/MW/day Hourly Short-Term Firm and Non-Firm Point-to-Point Transmission Service 01 $10.53/MW/h $10.80/MW/h Scheduling, System Control and Dispatch Service 03 $0.139/MWh $0.139/MWh
Read the Direction No. 9 to the British Columbia Utilities Commission on BC Laws ↗
Made under Utilities Commission Act, RSBC 1996, c. 473.