Dam Safety Regulation, B.C. Reg. 40/2016
Section 36
Transition — monitoring and review of dam safety
Cite as Dam Safety Regulation, B.C. Reg. 40/2016, s. 36 · last amended February 10, 2023 · read from BC Laws on November 17, 2026
The text
(1) For the purposes of section 18 (a) [site surveillance, formal inspections and tests], an owner of a previously unregulated dam must, on or before November 1, 2016,
(a) begin site surveillance of the dam, and
(b) conduct the first formal inspection of the dam.
(2) For the purposes of section 18 (b), an owner of a previously unregulated dam must, on or before November 1, 2016, conduct the first tests of the operation of
(a) the outlet facilities, spillway gates and other mechanical components of the dam, and
(b) the electrical and communication equipment relating to the dam.
(3) For the purposes of section 19 (1) (c) [instrumentation], an owner of a previously unregulated dam must, on or before November 1, 2016, begin collecting, analyzing and interpreting readings from the instrumentation relating to the dam.
(4) An owner of a previously unregulated dam that has a classification of high, very high or extreme must comply with section 20 (1) (a) and (b) [dam safety review and report] within 5 years after the date on which a dam safety officer gives notice to an owner of the dam that the dam safety officer accepts a proposed classification for the dam under section 31 [transition — dam failure consequences classification].
Read the Dam Safety Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.