Dam Safety Regulation, B.C. Reg. 40/2016

Section 13

Requirements if alteration or improvement to or replacement of dam

Cite as Dam Safety Regulation, B.C. Reg. 40/2016, s. 13 · last amended February 10, 2023 · read from BC Laws on November 17, 2026

The text

(1) An owner of a dam must, within 30 days after completion of an alteration or improvement to or replacement of all or part of the dam, submit to a dam safety officer (a) a written report on the work and the manner in which the alteration, improvement or replacement was performed, and (b) a copy of the as-built drawings. (2) A report under subsection (1) (a) may be combined with a report under section 14 (2) (a) [hazardous conditions], 15 (2) (a) [potential safety hazard] or 17 (5) [removing, decommissioning, deactivating or stopping operation of dam]. (3) An owner of a dam must, promptly after an alteration or improvement to or replacement of all or part of the dam is completed, (a) review and, if necessary, revise the operation, maintenance and surveillance manual and the emergency plan, if any, for the dam, and (b) submit to a dam safety officer for acceptance by the dam safety officer, (i) a record setting out the revisions, if any, or (ii) a written report advising that no revisions are necessary.
Read the Dam Safety Regulation on BC Laws ↗

Made under Water Sustainability Act, SBC 2014, c. 15.