Schedule 6 Table Relating to Well Identification Plates and Well Reports Column 1
Class of well Column 2
Category or
subclass Column 3
Well
identification
plate
required? Column 4
Well
construction
report
required?
(Schedule 3) Column 5
Well
decommission
report
required?
(Schedule 4) Column 6
Person to whom
well construction
report or well
decommission
report must be
submitted Water supply All water supply wells Yes* Yes Yes To the comptroller and well owner Monitoring Temporary No No No Not applicable Permanent No Yes Yes To the well owner Recharge or Injection Made by drilling or boring Yes Yes Yes To the comptroller and well owner Made by driving, jetting or excavating No No No Not applicable Dewatering Temporary No No No Not applicable Permanent Yes Yes Yes To the comptroller and well owner Remediation Temporary No No No Not applicable Permanent No Yes Yes To the well owner Geotechnical Borehole No Yes Yes To the well owner Closed-loop geoexchange All closed-loop geoexchange wells No Yes Yes One well construction report per geoexchange system to the comptroller and a report for every well in that system to the well owner All classes of well All flowing artesian wells If required above Yes Yes To the comptroller and well owner
* Well identification reports for water supply system wells under section 75 of the regulation use Schedule 2 and are submitted to the comptroller.