Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016
Section 28
Remission of annual rentals payable for water use plans
Cite as Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016, s. 28 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) In this section, “increased costs” includes increased costs to a licensee resulting from a condition of an order, new licence or amended licence, referred to in subsection (2) (c), that requires the licensee to collect, analyze or report specified information to the comptroller.
(2) Authorization is given for remission of part of the annual rentals payable in respect of a power development if all of the following apply in relation to the licensee of the power development:
(a) on request of that licensee the comptroller has completed a review of the licences in respect of the power development and made any changes to the licence that are necessary to provide
(i) a clear description of the rights granted and obligations imposed in respect of the power development, and
(ii) a basis for monitoring compliance with and enforcement of the licences and the terms and conditions of the licences;
(b) the licensee has
(i) completed a water use plan in respect of the power development in accordance with the Water Use Plan Guidelines published by the government and dated December 1998, and
(ii) submitted the water use plan to the comptroller for review;
(c) the comptroller has ordered or authorized the licensee to operate the power development as contemplated by the water use plan, either as submitted or as modified by the comptroller, including by or as a condition of
(i) an order made under section 93 of the Act,
(ii) a new licence issued under section 14 [powers respecting applications and decision maker initiatives] of the Act, or
(iii) a licence amended under section 26 [amendment or substitution of authorization, change approval or permit] of the Act;
(d) the order, new licence or amended licence was in effect in the preceding calendar year;
(e) compliance with the order, new licence or amended licence has had the effect of
(i) a net loss of revenue to the holder from power production, or
(ii) increased costs to the holder
at the power development that is the subject of the order, new licence or amended licence, in favour of benefits other than power benefits, that did not accrue to the licensee and that may include benefits for fish, fish habitat, flood protection, recreation or otherwise;
(f) the licensee provided, for the preceding calendar year, as directed by the comptroller, information on
(i) the operation of the power development, or
(ii) any other aspect of the power development;
(g) the comptroller is satisfied that the licensee substantially complied with the order, new licence or amended licence during the preceding calendar year.
(3) The authorization for remission under subsection (2) is subject to the condition that the total amount of the remission, as determined under subsection (4),
(a) in respect of the Peace River Water Use Plan, is set out in a remission schedule that has been
(i) approved by the Lieutenant Governor in Council, or
(ii) varied by, and approved as varied, by the Lieutenant Governor in Council, or
(b) in respect of all other water use plans, is set out in a remission schedule approved by the chair of Treasury Board.
(4) Subject to subsections (3) (a) and (5), the amount to be remitted under subsection (2) in a calendar year is to be
(a) equal to the amount calculated using the following formula: net loss of revenue + (increased costs - net gain in revenue),
(b) determined by applying a methodology as agreed by the licensee and the comptroller or, failing agreement, as may be otherwise established by the comptroller, for
(i) calculating the net loss of and net gain in revenue to the licensee from power production, and the increased costs to that licensee, at the power development that have resulted from compliance with an order, new licence or amended licence referred to in subsection (2) (c) in respect of the power development, and
(ii) a schedule, covering a period not longer than 20 years, for remission to the licensee of annual rentals payable by that licensee in respect of the power development as calculated in accordance with paragraph (a) and subparagraph (i) of this paragraph, beginning in the calendar year following the calendar year in which the order, new licence or amended licence referred to in subsection (2) (c) is made or issued, and
(c) deducted from the total annual rentals payable by the licensee in respect of the power development.
(5) The total amount of remissions authorized under this section in each calendar year must not exceed $50 million.
(6) If section 7 [rentals due 1/2 yearly if rentals exceed $100 000] applies in relation to annual rentals referred to in subsection (2), an estimate of 1/2 of that calendar year's remission must be deducted from the first instalment and the balance of that calendar year's remission must be deducted from the second instalment.
Read the Water Sustainability Fees, Rentals and Charges Tariff Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.