Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016
Section 22
Additional fees in respect of certain downstream benefits
Cite as Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016, s. 22 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) In this section:
“downstream hydroelectric plant” means a hydroelectric plant located outside British Columbia and downstream from a storage facility operated in British Columbia by a licensee under the authority of a licence for storage purposes;
“downstream owner” means an owner, part owner or operator of a downstream hydroelectric plant.
(2) Subject to subsection (8), the holder of an authorization for storage purposes who
(a) operates a storage facility for the purpose of enabling a downstream hydroelectric plant to generate greater amounts of electricity than the amount the hydroelectric plant could generate if the storage facility were not available, and
(b) receives a benefit for doing so from a downstream owner
must pay the fees determined under this section in addition to any fees, rentals or charges payable by the authorization holder for storage purpose under any other provision of this regulation.
(3) The additional fee referred to in subsection (2) is to be determined at the applicable rate under Table 2 of Schedule 2 for annual rentals for output.
(4) For the purposes of subsection (3), the rate for output is the higher of the following:
(a) the rate applicable to the authorization holder in determining the other annual rentals upon output payable by that holder under this regulation for the calendar year in which the fee is payable;
(b) the rate that would be applicable to the downstream owner in determining annual rentals if the downstream plant were in the Province and the downstream owner were a licensee.
(5) If the holder of an authorization for storage purposes is also the downstream owner, the additional fee referred to in subsection (2) is to be based on the amount by which the hydroelectric energy available at the downstream hydroelectric plant increases due to the operation of the upstream storage facility.
(6) If, in return for operating an upstream storage facility, an authorization holder who is not a downstream owner receives hydroelectric energy from the downstream owner, the additional fee referred to in subsection (2) is to be based on the amount of hydroelectric energy so received.
(7) If, in return for operating an upstream storage facility, an authorization holder who is not a downstream owner receives benefits other than hydroelectric energy from the downstream owner, the additional fee referred to in subsection (2) is the fee that the holder would be required to pay under this section if that holder were a holder described in subsection (5) and receiving 1/2 of the amount by which the hydroelectric energy generated by the downstream plant is increased due to the operation of the upstream storage facility.
(8) Fees determined under this section are payable in the calendar year following the calendar year in which the licensee incurs the fee, but, for the purpose of the fee calculation under this section, the rate for output is the rate for output for the calendar year in which the fee is payable, despite the fee having been incurred in the preceding calendar year.
(9) This section does not apply to the power benefits described in the Columbia River Treaty as the Canadian entitlement.
Read the Water Sustainability Fees, Rentals and Charges Tariff Regulation on BC Laws ↗