Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016
Section 2
Application fees
Cite as Water Sustainability Fees, Rentals and Charges Tariff Regulation, B.C. Reg. 37/2016, s. 2 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) The following fees are prescribed for the purposes of section 12 (1) (b) (ii) [application and decision maker initiative procedures] of the Act:
(a) for a licence or use approval for one or more water use purposes, or classes of water use purpose, other than a power purpose, the sum of the application fees set out in column 2 of Table 1 of Schedule 1 opposite each water use purpose or class of water use purpose, set out in column 1, to which the application relates;
(b) for a change approval, the amount set out in column 2 of Table 4 of Schedule 1 for a change approval;
(c) for a class of permit set out in column 1 of Table 3 of Schedule 1, the amount set out opposite in column 2 for a permit in the class;
(d) for the issuance of a final licence, the amount payable under paragraph (e) (i) or (ii), as applicable, as if the application were for an amendment under section 26 [amendment or substitution of authorization, change approval or permit] of the Act;
(e) for an amendment under section 26 of the Act, a transfer of appurtenancy under section 27 [transfer of appurtenancy] of the Act, an apportionment under section 28 [apportionment of rights under licences] of the Act or an amendment to a drilling authorization under section 62 [drilling authorizations] of the Act,
(i) in the case of a licence or use approval that authorizes only one water use purpose, the amount set out in column 3 of Table 1 of Schedule 1 opposite that purpose in column 1 or, if the water use purpose is power purpose, the amount set out in column 3 of Table 2 of Schedule 1 opposite the applicable power use category and class of that category in column 1,
(ii) in the case of a licence or a use approval that authorizes the use of water for more than one purpose, the highest of the amounts set out, as applicable, in column 3 of Table 1 of Schedule 1 opposite those water use purposes in column 1 or in column 3 of Table 2 of Schedule 1 opposite the applicable power use category and class of that category in column 1,
(iii) in the case of a change approval, the amount set out for a change approval in column 3 of Table 4 of Schedule 1,
(iv) for a class of permit set out in column 1 of Table 3 of Schedule 1, the amount set out opposite in column 3 for a permit in the class, and
(v) for a drilling authorization, the amount set out for a drilling authorization in column 3 of Table 4 of Schedule 1;
(f) for a drilling authorization, the amount set out in column 2 of Table 4 of Schedule 1 for a drilling authorization;
(2) A separate fee under subsection (1) is payable in relation to each licence, use approval, change approval, permit and drilling authorization that is to be issued or amended under the application.
(3) Despite subsection (1) but subject to subsection (2), only the applicable fee under subsection (1) (e) (i) or (ii) is payable if an application relates to more than one of
(a) an amendment under section 26 of the Act,
(b) a transfer of appurtenancy under section 27 of the Act, and
(c) an apportionment under section 28 of the Act.
Read the Water Sustainability Fees, Rentals and Charges Tariff Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.